Siam Paragon Luxury Property Showcase

The Siam Paragon Luxury Property Showcase returns for the year 2011 and from 3-13 March Raimon Land will be featuring our most exclusive freehold condominium development to date, 185 Rajadamri.
Secure your unit only with your credit card to earn a substantial amount of reward points with our Go Cashless promotion. To find out more about this special offer and other exciting promotions, visit our booth on M Floor, Hall of Fame, Siam Paragon.

|
The River 10/90

Embark on a lifestyle of convenience at The River today with our special payment scheme that reduces the hassle of making multiple payments prior to ownership transfer.
The River 10/90 presents a distinctive range of 19 units at The River for your selection as we split your payments into just two portions - 10% now and 90% upon transfer.
For more information and to register your interest, please click here or call 02-651-9600.

|
Go Cashless with Raimon Land

Raimon Land in conjunction with Thailand's leading credit card companies present a flexible payment solution for prospective clients to own any four of our luxury condominium projects - 185 Rajadamri, The River, Northpoint and Zire Wongamat.
Forget carrying cash or writing cheques and pay the initial 10% contract signing fee with your favorite card to earn a substantial amount of reward points as Raimon Land absorbs all credit card processing fees.
For more information and to register your interest, please click here or call 02-651-9600.

|
The River

Project progress up to the end of February continued according to programme.
The South Tower's structure has topped out at Level 71, structural works are now commencing for the building crown; while the North Tower's structure was topped out at level 43 in October 2010. The overall podium structural progress (podium A, B and C) remains at 99.88% finished, Cooling Towers and staircases are now complete. Works for Hardscape have been awarded and contractors are mobilising, Softscape works on Level 5 Podium Deck are about to be awarded. South Tower Glass Curtain Walls installation has reached Level 62, Window Wall system has reached Level 42; North Tower Glass Curtain Walls installation has reached Level 35 and Window Wall system has reached Level 30 in North Tower.
First fix Mechanical (fire, sanitary and HVAC systems) and Electrical services are ongoing up to Level 50 South Tower and Level 37 North Tower.
Civil and External Works on roads, boundary fence, drainage, retention tanks are progressing.
To read the full construction update and see more photos, click here or alternatively, follow The River on Facebook.

|