The River

Project progress up to the end of May continued according to programme.
Both the South and North Tower's structure has been completed; the structural works for the building crown is ongoing. The overall podium structural progress (podium A, B and C) remains at 99.88% finished, the Hardscape finishing works are progressing throughout the Podium and surrounding Ground Floor areas. Cooling Towers and staircases are now complete. Softscape works on Level 5 Podium Deck are about to be awarded. South Tower Glass Curtain Walls installation has reached Level 67, Window Wall system has reached Level 57; North Tower Glass Curtain Walls installation has reached Level 41 and Window Wall system has reached Level 38 in Tower B. In both Towers installation of glass balustrades has been commensurate with Curtain Wall installation.
Critical Path works of Architectural trades, MEP and finishing trades is now intensifying with Architectural works, including unit partition walls, masonry and plastering, have reached up to Level 68 Tower A; Level 42 Tower B and works are ongoing. Internal Ceiling works to corridors, Lift Lobbies, Unit Bathrooms and wall/floor tiling/wood flooring are commencing. First fix Mechanical (fire, sanitary and HVAC systems) and Electrical services are ongoing up to Level 59 Tower A and Level 41 Tower B. Subsequent trade activities for the M&E 2nd fix trades activities is progressing to allow the commencement of ceiling closures. Testing of Mock-Up Suites HVAC systems is complete subject to final adjustment and balancing. Main MEP Plant including transformers, Stand-By Generators and Main Distribution Boards are now on site awaiting installation. Vertical riser pipes for all mechanical and water services are advancing. Sanitary appliances, fan coil units and condenser units are on site together with floor and wall tiles.
Passenger and Service lifts have arrived on site with guide rails installation works continuing. CTU (Construction Lifts) are have been commissioned and are operational for construction services up to Level 40. Final fix of the CTU lifts to high zone will be completed by end of May.
The first Mock-up Kitchens are complete and approved; project manufacture has begun and will continue according to programme. Residential Levels Lift Lobby contracts have been awarded and installation commenced. Delivery schedules of domestic appliances have been agreed and the appliances are being prepared for delivery to site.
Civil and External Works on roads, boundary fence, drainage, retention tanks are progressing. Test panels of Car Park/Podium cladding have been erected for inspection and approval.
To read the full construction update and see more photos, click here or alternatively, follow The River on Facebook.

|