The River – Construction update

Project progress up to the end of June continued according to programme.
Both the South and North Tower's structure has been completed; the structural steelworks for the building crown is complete awaiting secondary framing and partial glazing. The overall podium structure (podium A, B and C) remains at 99.88% finished, the Hardscape finishing works are progressing throughout the Podium and surrounding Ground Floor areas. Softscape works on Level 5 Podium Deck have been awarded. South Tower Glass Curtain Walls installation has reached Level 70, Window Wall system has reached Level 67; North Tower Glass Curtain Walls installation is complete to Level 41 and Window Wall system has reached Level 41 in Tower B. Installation of glass balustrades has reached Level 68 Tower A and is 100% complete in Tower B. Structural steelwork for Entrance Drop Off canopies is well developed.
Critical Path works of Architectural trades, MEP and finishing trades is now intensifying with Architectural works, including unit partition walls, masonry and plastering, have reached up to Level 71 Tower A and have been completed in Tower B. Internal Ceiling works to corridors have reached Level 34. Lift Lobbies, Unit Bathrooms and waterproofing/wall/floor tiling/wood flooring are ongoing. First fix Mechanical (fire, sanitary and HVAC systems) and Electrical services are ongoing up to Level 62 Tower A and Level 41 Tower B. Subsequent trade activities for the M&E 2nd fix trades activities is progressing to allow the commencement of ceiling closures. Testing of Mock-Up Suites MVAC systems is complete and the MVAC installations are now progressing in the residential Units. Main MEP Plant including transformers, Stand-By Generators and Main Distribution Boards site installation is progressing. Vertical riser pipes for all mechanical and water services are advancing.
The Kitchens have been received on site and installation is commencing according to programme. Passenger and Service lifts are complete and being employed as CTU (Construction Lifts to enable movement of construction workers) and will be serviced before final commissioning for public use. Lift car fit out contract has been awarded. Residential Level Lift Lobby contracts have been awarded and installation is ongoing. Contracts have now been awarded for the Main Lobbies fit-out, Gymnasiums, Sky Garden works. Delivery schedules of domestic appliances have been agreed and the appliances are being prepared for delivery to site.
Civil and External Works on roads, boundary fence, drainage, retention tanks are progressing. Test panels of Car Park/Podium cladding have been erected for inspection and approval. Principal Utility connections and incoming services have been contracted to appropriate authorities for installation.
To read the full construction update and see more photos, click here or alternatively, follow The River on Facebook.

|