August 2010 works at the Northpoint project are nearing to completion of the project. Corridors are substantially complete and the remaining penthouses Tower A and upper units PRC Tower B near final trades works completion. Home owner inspections are continuing according to hand over programme.
Apartment fit-out works are nearing completion, with corridors, fire escape stairs and common areas now completed. All external cleaning of all facades, aluminium and glass and external louvers have been completed. Sky gardens at level 29 tower A and level 24 tower B are complete and gymnasiums have been equipped and tested. All management offices and back of house facilities are occupied and functional.
Final mechanical & electrical, fire protection and waste water system are operational.
Externally, swimming pools, slides and water feature works all operational and in full use. Canopies to the car drop-off zones are complete. The main entrance guard house and site boundary wall construction works are complete while final finishes to the road surfaces have now been completed.
Car park building roof-top the tennis court is complete. The car park building painting works have been completed together with planter box façade installations and irrigation systems. Additional improvements to weatherproof the car park lift lobbies together with some minor finishing improvements are nearing completion. Security controls and access systems are now fully operational.
To read the full construction update and see more photos, click here or alternatively, follow Northpoint on Facebook.

|