Construction Updates
The River

Construction of The River in the month of April continued to make solid progress. Both the basement slab and the first floor slab of the South Tower are now 100% complete, while the basement slab of the North Tower is 100% complete and the first floor slab 75% complete. Installation of the fifth and final tower crane has been completed which will be utilized to distribute construction materials from the stock yard to the main project area.
Meanwhile, at the Podium the isolated footing is 98% complete and the basement slab is 82% with the first floor slab 10% complete.
To better illustrate how this landmark development is taking shape on the banks of the Chao Phraya River, this month we're pleased to bring you some spectacular aerial shots of The River. Click here for an exclusive look.

Northpoint

Through April 2009 Northpoint continued to make progress despite the Songkran Holiday shutdown period. The demolition works at the beachfront sales offices and show unit building are now practically complete allowing for imminent commencement of the landscape package works to the 12-rai site. The new show units and sales offices have been re-located to level 3 of tower A and are facilitated by a new covered walkway that has been constructed between the sales office car park and Tower A.
Mechanical, Electrical and Plumbing first fix installations have progressed towards the penthouse levels, and the second fix installations are progressing significantly at both towers. The lift package works are due to be commissioned shortly for temporary services during the works and are significantly advanced in terms of overall progress.